Transmission - K-Electric

Transmission

Merit Order Sheet


The transmission system of KE comprises of 1350km of 220kV, 132kV and 66kV lines, with 71 grid stations, 20 auto transformers and 179 power transformers.

 

transmission-timeline

With a vision to supply uninterrupted electricity and to bridge the gap between valued customers and K-Electric, a significant investment is made in recent years. Major initiatives were taken in areas of Capacity Enhancement, Grid station and Transmission line augmentation and rehabilitation.

Transmission System Enhancement

Owing to the investment made in transmission system, the MVA capacity increased by over 2600 MVA and the overall transmission losses improved by 2.93% points since the start of FY09.

transmission-timeline
transmission-timeline

Following grid stations have been added in the system

transmission-timeline

List of Transformers installed in the system post July’ 2018:

40 MVA

Hub Chowki

October 2018

40 MVA

Surjani

October 2018

40 MVA

Valika

November 2018

40 MVA

Elander Road

December 2018

40 MVA

Shadman

December 2018

40 MVA

Mauripur

January 2019

40 MVA

Shadman

January 2019

40 MVA

Old Town

January 2019

40 MVA

KEPZ

January 2019

40 MVA

Malir

January 2019

40 MVA

Port Qasim

February 2019

40 MVA

PRL

March 2019

40 MVA

Old Golimar

March 2019

40 MVA

Old Golimar

March 2019

40 MVA

Qayyumabad

April 2019

40 MVA

Queens Road

April 2019

40 MVA

Valika

April 2019

40 MVA

KDA

June 2019

40 MVA

Baldia

July 2019

40 MVA

Creek City

August 2019

10 MVA

Gadap

October 2019

40 MVA

Creek City

November 2019

40 MVA

Labour Square

November 2019

40 MVA

Labour Square

November 2019

40 MVA

Pipri West

December 2019

40 MVA

DHA-1

December 2019

40 MVA

AKUH

December 2019

40 MVA

Queens Road

February 2020

40 MVA

Federal-B

February 2020

40 MVA

Defence

February 2020

40 MVA

BOC

February 2020

40 MVA

Garden East

March 2020

40 MVA

Hub Chowki

July 2020

39 MVA

KDA

September 2020

40 MVA

Maymar

January 2021

40 MVA

Mehmoodabad

March 2021

40 MVA

Mehmoodabad

March 2021

Major Projects

Cross Trip Scheme and Rehabilitation of 220kV KDA – Jamshoro circuits

To meet the increasing demand of metropolis, K-Electric alongside increasing its own generation capability also proposed to offtake additional power from National Grid up to 1100 MW. To ensure the reliability of the system post increased drawl from NTDC “Cross Trip Scheme” project was required to be initiate.

Alongside implementation of cross trip scheme, it was pivotal to rehabilitate 220kV KDA – Jamshoro circuits of NTDC to ensure additional power offtake. The rehabilitation project was jointly undertaken by NTDC and KE.

Both, the implementation of Cross Trip Scheme and Rehabilitation of 220kV KDA – Jamshoro circuits, were achieved well with in projected timeline that helped in managing the demand – supply situation efficiently.

New Interconnection Points with NTDC for Evacuation of Additional Power

KE, for benefitting consumers and economy at large has conceived projects of 500kV KKI and 220kV Dhabeji grid stations as additional interconnections with NTDC, considering the surplus supply scenario in National grid. With new interconnections KE will be able to import 2050 MW power from NTDC which will enable KE to manage the demand in upcoming years alongside enhancing system reliability. Both the projects are accelerating on fast pace which reflects KE’s promise for the betterment of Karachi.

Hub, Vinder, Uthal & Bela (HVUB) Project

KE has planned to bring a substantial change in the rural parts of its service territory by upgrading its infrastructure in these areas to meet the increasing load profile and to help economic expansion. In this respect, KE has planned to erect a new double circuit of 132kV transmission line from Hub-Chowki to Bela grid and enhancement of grids in Vinder, Uthal & Bela from 66 kV to 132 kV level. The project will be completed by September 2023 with cost of PKR 7,325 million.

In addition to the above, rehabilitation of existing 132kV and 66 kV transmission lines in this loop is also under execution. Phase 1 of the project has already been kicked off with 65% of scope executed so far. Meanwhile, in parallel the execution of phase 2 is expected to be initiated from September 2021.

TP-1000

To meet the growing load demand, project of over USD 450 million was conceived and by far, 6 new grid stations and 27 power transformers, along with rehabilitation of around 39.16 km and net addition of 47.94 km line length is attained. The state of the art “Disaster Recovery Centre (DRC)” facility is also commissioned under the canopy of this project which will serve as backup for KE load dispatch center thus providing redundancy for continuing the uninterrupted supply in case of any exigency.

GIS Overhauling Project

Capacity enhancement project is conceived for both HIS and GIS grid stations that is on course of its successful completion. By far, seventy-seven (77) bays have been completely retrofitted and the project is on course of its target achievement.

Grid Capacity Enhancement Projects

Capacity enhancement project is conceived for both HIS and GIS grid stations that are on course of their successful completion. The project encapsulates addition of 31.5/ 40MVA Power Transformers, 132kV GIS bays and allied MV switchgear at grid stations.

In addition to the above, the Company has also taken initiatives for replacement of obsolete current/ potential transformers, circuit breakers and relays and, rehabilitation of various EHT transmission lines, whereby conductors, insulators and associated hardware are replaced. Moreover, quarterly line insulator cleaning activities, annual preventive maintenance activities, thermography (predictive maintenance), RTV coating of insulators and installation of composite insulators helped improve the reliability of circuits near coastal belt by way of enhanced performance against humidity and pollutants and ensured smooth network operational capability.

Enhancement in SCADA systems and functionality is another systematic approach that has enabled to effectively trail and monitor the network remotely.

WordPress Lightbox